What Regulation 38 requires
Regulation 38 of the Building Regulations 2010 applies where building work involves the erection or extension of a building, or a material change of use, and the completed building will fall under the Regulatory Reform (Fire Safety) Order 2005. The person carrying out the work must give fire safety information to the responsible person no later than the date of completion, or the date of occupation if that's earlier.
That information covers the design and construction of the building and the services, fittings and equipment provided, so the responsible person can operate and maintain the building with reasonable safety. For higher-risk buildings, information is also handed over to the accountable person as part of the golden thread at completion.
What is a Regulation 38 review?
A Regulation 38 review is an independent check of that handover information. We compare what has been provided with what the responsible person actually needs, identify what's missing or inconsistent, and produce a clear list of information to request – or help assemble it, including an as-built fire strategy where none exists.
Who needs one
- Developers and contractors who want to hand over a complete, defensible package at practical completion
- Freeholders, managing agents and landlords taking on a newly completed, extended or converted building
- Owners of recently completed buildings whose fire risk assessment keeps flagging missing design information
- Purchasers and investors checking that a new asset comes with the fire safety information it should – see fire safety due diligence
What documents are required under Regulation 38?
The regulation doesn't list documents, but Approved Document B and industry guidance describe what a good handover contains. We check for:
- The as-built fire strategy and fire strategy drawings
- The evacuation strategy and how the alarm system supports it
- Commissioning certificates and specifications for fire safety systems – detection and alarm, emergency lighting, smoke control, sprinklers, dry or wet risers and firefighting lifts
- The cause-and-effect schedule for interlinked systems
- Fire door and fire damper schedules
- Fire-stopping and cavity barrier records, ideally with photographs taken before ceilings were closed up
- External wall build-ups and the test evidence for the products used
- Maintenance and testing requirements for each system
- Any departures from guidance and the management assumptions the design relies on
Read more in our guide to Regulation 38 and the fire and emergency file.
What's included
- Review of the handover pack and O&M manuals
- Check against Regulation 38 and Approved Document B
- Consistency check with drawings and the fire strategy
- Gap list with priorities
- Information request schedule for the developer
- As-built fire strategy where none exists
- Fire strategy drawings
- Advice for the first fire risk assessment
- Golden thread handover check for higher-risk buildings
- Plain-English summary for the client
Regulation 38 review fees
Fees depend on the size and complexity of the building and on how complete the handover information is. A desktop review of a well-organised pack is quick; rebuilding missing information, or preparing an as-built fire strategy, takes longer. We confirm a fixed fee before you commit – see the cost guide.
Where we work
Regulation 38 reviews are carried out for buildings in London, Slough and Berkshire, and across the UK.
Related services
- Fire Strategy Reports – for new builds, refurbishments and changes of use
- Retrospective Fire Strategies – for existing buildings with a missing or outdated strategy
- Building Safety Act Consultancy – gap analysis, golden thread and Gateway support